Skip to main content

Manage a Task for a Technique

Intel Exchange enables you to manage a task to change its status.

Steps

To manage a task, follow these steps:

  1. Go to Main Menu > Analysis > ATT&CK Navigator.

  2. Select a layer.

  3. Select a technique to open the technique details.

  4. Go to Tasks, and select an existing task.

  5. Click the ellipsis(...), and choose from the following options:

    • To shift the task to In Progress status, select Move to In Progress. 

    • To shift the task to Completed status, select Mark as complete and enter a closure comment.

    • To modify the details, select Edit.

    • To remove the task, select Delete.